top of page

Your Fit-Out Contractor Is Behind Schedule and Getting Worse.Here Is What You Can Actually Do About It.

Writer: UODC Architects Marketing
UODC Architects Marketing
4 minutes ago
11 min read

Most corporate clients do not know what their legal options are when a contractor underperforms, delays, or disappears. That ignorance is expensive. The Philippine Civil Code gives you more tools than you probably realise. The problem is that by the time most companies look for them, they have already made decisions that weakened their position.

This is a situation no company plans for and almost every company eventually faces in some form.


The contractor was on schedule in week one. By week four, the programme had slipped two weeks. By week eight, calls were going unreturned. By week twelve, the site had fewer workers than agreed, the project manager you were promised had been reassigned to another job, and your move-in date — which your lease and your operations both depend on — was no longer going to happen.


What do you do?

My view is direct: most companies in this situation wait too long to act. They send follow-up emails, accept explanations, extend goodwill, and lose six weeks of leverage in the process. By the time they decide to take a formal position, the contractor has received most of the money, the project is 60% complete, and the options have narrowed considerably. The time to act on a contractor problem is the moment you see it. Not when you have confirmed it beyond all doubt.

This article walks through the stages of a contractor failure, what your rights are at each stage under Philippine law, and the specific actions that protect your position while keeping the project moving wherever possible.






3 in 5

Corporate fit-out projects in Metro Manila experience contractor-related delays significant enough to push the move-in date by four weeks or more. Of these, fewer than one in three clients formally documented the delay and its causes in writing at the time it began. That documentation gap is the single biggest reason delay costs are difficult to recover.


Section 1

Know what stage you are in — because the right action is different at each one


A contractor problem is not a single event. It develops in stages, and each stage calls for a different response. The mistake most clients make is treating a Stage 2 problem with Stage 1 patience, or escalating a Stage 1 problem with Stage 3 aggression. Both approaches cost you.


Stage 1  —  SLIPPAGE — THE PROGRAMME IS BEHIND BUT THE CONTRACTOR IS STILL ENGAGED


The project is running late but the contractor is present, communicating, and providing explanations. The delay may be due to permit processing, material availability, restricted working hours, or subcontractor scheduling. Some slippage at this stage is normal. The question is whether the contractor has a credible recovery plan and is executing it. YOUR SIGNAL: Is there a revised programme in writing, with specific dates and deliverables? If the answer is no after two requests, you are not in Stage 1 anymore.

Stage 2  —  PERFORMANCE FAILURE — THE CONTRACTOR IS PRESENT BUT NOT DELIVERING


Work is continuing but at a pace that cannot recover the programme. The number of workers on-site is below what the contract requires. Quality is below specification. The contractor is generating change orders to recover margin rather than executing the agreed scope. This is the stage where most clients make the most expensive mistake: continuing to pay progress billings without requiring the corresponding progress. YOUR SIGNAL: At each billing, ask for a site survey showing percentage completion by trade. If the billed completion exceeds actual completion, you are being overbilled for work not yet done.

Stage 3  —  ABANDONMENT OR NEAR-ABANDONMENT — THE CONTRACTOR HAS EFFECTIVELY STOPPED


Workers have left the site. Communication has broken down. The contractor is not responding to formal notices. Equipment has been removed from the site. Subcontractors have told you they have not been paid. This is a crisis with a hard clock: every day without a contractor on-site is a day your lease is running and your move-in date is moving further away. YOUR SIGNAL: If the site has been unmanned for more than five consecutive working days without written notice and a resumption date, treat this as abandonment. Do not wait for further confirmation.


Section 1

Your rights under Philippine law

The Civil Code of the Philippines gives corporate clients significant rights when a contractor fails to perform. Most clients do not know they exist. Here is what the law actually provides.


  1    The right to demand performance with a fixed deadline

 —  Civil Code, Article 1169


If your contractor is in delay, you have the right to place them in default by serving a written demand specifying a deadline for compliance. This is called a demand letter or notice of default. Once served, the deadline starts running formally. If the contractor does not comply within the stated period, you have grounds to terminate the contract and claim damages. A verbal demand does not trigger this. It must be in writing, dated, and documented.


  2    The right to have defective work corrected at the contractor’s expense   

—   Civil Code, Article 1715


If the contractor’s work does not conform to the contract specifications, you have the right to demand correction at no additional cost to you. This includes substandard finishes, incorrect dimensions, materials that differ from specifications, and work that does not meet the approved drawings. Document every defect with photographs, dates, and written notice to the contractor. A defect you accept in silence may be considered accepted.


  3    The right to rescind the contract and engage another contractor   

—   Civil Code, Articles 1191 and 1726


If the contractor has fundamentally failed to perform — through abandonment, persistent delay despite demand, or material breach — you may rescind the contract and engage another contractor to complete the works at the defaulting contractor’s expense. This right is not absolute: you must have documented the breach, served a formal demand, and given the contractor a reasonable opportunity to remedy. Rescinding without this sequence weakens your position significantly.


  4    The right to recover actual damages   

—   Civil Code, Articles 2199–2205


You can claim actual damages for losses caused by the contractor’s failure: the cost of engaging a replacement contractor at higher rates, extended rent on your existing premises, temporary accommodation costs, storage costs for furniture and equipment held off-site, and productivity losses from staff unable to operate from the new space. Every recoverable cost must be documented with receipts and a clear causal link to the contractor’s breach.


  5    The right to enforce liquidated damages clauses   

—   Civil Code, Article 2226


If your contract includes a liquidated damages clause — specifying a daily or weekly penalty for delay — you may enforce it without needing to prove the exact amount of loss. The agreed penalty is presumed to represent the pre-assessed value of the delay. If your contract does not include this clause, you must prove actual loss to recover delay damages. This is one of the most important reasons why the liquidated damages clause should be in every fit-out contract before it is signed.

THE MOST IMPORTANT CONTRACT CLAUSE YOU MAY NOT HAVE

A liquidated damages (LD) clause specifies a fixed daily or weekly penalty for every day the project runs beyond the agreed completion date. Without it, proving delay damages in court requires quantifying each specific loss, which is time-consuming, expensive, and uncertain. With it, you can enforce the penalty as soon as the deadline passes, without needing to prove the exact cost of the delay. If your current fit-out contract does not include an LD clause, negotiate one before work begins. If the contract is already signed without one, document every delay cost meticulously from today.

Section 3

The seven steps to take when a contractor is failing

These steps work sequentially. Each one protects your position for the next. Skipping steps is the most common reason companies lose disputes that should have been straightforward.


  1    Stop approving progress billings without verifying completion

Every progress billing should be accompanied by a site survey showing percentage completion by trade, against the agreed programme. If the contractor is billing 70% complete on electrical works and your own assessment shows 50%, pay 50%. Document the shortfall in writing when you make the partial payment. This is not a dispute — it is a contractual right. Paying in full for work not yet done is the single fastest way to exhaust your leverage before the dispute is formally acknowledged.


  2    Issue a formal written notice of delay

Do not manage delay by phone call or WhatsApp message. Send a written notice, dated and addressed to the contractor’s principal, stating the current programme status, the number of days of delay as of that date, and a specific deadline by which the contractor must submit a written recovery plan. Ten business days is a reasonable period. Send it by email and by registered mail. Keep proof of delivery. This document is the start of your formal record.


  3    Demand a written recovery programme with specific milestones

A verbal commitment to ‘catch up’ is not enforceable. A written programme with milestone dates and deliverables is. If the contractor produces one, hold them to it explicitly: issue a written acknowledgement that you have accepted the programme and that failure to meet any milestone will constitute a further breach. If the contractor does not produce a recovery programme within your stated deadline, note that failure in writing and proceed to step four.


  4    Conduct a formal site assessment and document everything

Engage an independent quantity surveyor or project manager to assess the actual state of completion against the approved drawings. Photograph every area of the site with date stamps. Document materials on-site, materials not yet delivered, and the number of workers present on each visit. This assessment is your evidence. It establishes the actual completion percentage at the time of any dispute and protects you from a contractor who claims more progress than exists.


  5    Send a formal notice of default and demand for remedy

This is a legal document, not a strongly worded email. It should be prepared or reviewed by a lawyer. It formally places the contractor in default, states the specific breaches, quantifies the delay in days, states the liquidated damages accrued to date if your contract provides for them, and gives a final deadline for remedy — typically 14 to 21 days — after which you will exercise your right to terminate and engage a replacement. Send it by registered mail. This document starts the clock on your termination rights.


  6    Engage a replacement contractor on a concurrent basis

If the original contractor does not respond to your notice of default with a credible and immediate remedy, begin the process of engaging a replacement contractor before you terminate. Get at least two quotes for completion of the remaining works. Document the scope of remaining works based on your site assessment. The difference between the original contract value of the remaining works and the cost of the replacement contractor is a recoverable cost from the defaulting contractor. Do not wait until after termination to start this process — every day without a contractor on-site is a cost you are accumulating.


  7    Formally terminate the contract and preserve the retention

Once the notice of default period has passed without remedy, issue a written notice of termination citing the specific breaches, the notices previously served, and your intention to engage a replacement contractor. Do not release any retained funds. The retention — typically 5 to 10% of the contract value held back until practical completion — is your primary security against the contractor’s failure. It should only be released, if at all, after the replacement contractor has completed the works and all breach-related costs have been quantified.


Section 4

What to do when the contractor has disappeared

Abandonment is the most acute version of contractor failure. No workers on-site. No response to calls or messages. Potentially, the contractor’s principals are unreachable. This situation has a different urgency because your project is completely stopped and your lease clock is running.

When a contractor abandons a project, companies typically spend the first week in disbelief and the second week trying to reach someone. By week three, they’re finally talking to a lawyer. That three-week gap is the most expensive delay in the entire project. If the site has been unmanned for five consecutive working days without written notice from the contractor, treat it as abandonment and act today. Not next week.

✓  Immediately secure the site and document its condition.  If the contractor has left tools, equipment, or materials on-site, do not remove or use them. Photograph and inventory everything. Change the access credentials or locks if you control the space. Notify building management in writing that the original contractor has abandoned the project and that you are taking steps to secure the site.


✓  Serve formal abandonment notice by registered mail to the contractor’s registered address.  Even if you cannot reach them, serve the notice to their last known address and their registered address with the Securities and Exchange Commission or the Department of Trade and Industry. This creates a legal paper trail that the notice was served. If the contractor later disputes the abandonment, your documented attempts at service are critical.


✓  Notify your landlord and building management immediately.  Your lease is running. Your landlord needs to know why you are not progressing toward the agreed move-in date. They also need to confirm whether your fit-out approval is affected by the change of contractor. Some buildings require re-approval when the accredited contractor changes. Find out now, not when you are weeks into a replacement contractor’s work.


✓  Engage a lawyer the same week.  Abandonment gives you the right to terminate immediately and engage a replacement. But termination without proper documentation and proper legal process can expose you to a counter-claim from the original contractor asserting wrongful termination. A single lawyer’s letter, drafted correctly and served properly, costs a fraction of the dispute it prevents.


✓  File a complaint with the Philippine Contractors Accreditation Board (PCAB). 

If your contractor holds a PCAB licence — which they are legally required to have for construction work — abandonment of a project is grounds for suspension or revocation of that licence. Filing a complaint does not guarantee immediate remedy, but it creates a formal record and signals that you are taking all available recourse. PCAB complaints can also be referenced in civil proceedings.


Section 5

The provisions that protect you - before any of this happens.


The best time to deal with a contractor problem is before the contract is signed. These are the clauses that experienced corporate clients insist on because they have been through a contractor failure without them.


✓  Liquidated damages clause with a specific daily rate.  Agree in advance what each day of delay costs. A typical rate is 0.1% of the contract value per day, capped at 10 to 20% of the total contract price. On a ₱20 million fit-out, that is ₱20,000 per day. It makes every delay expensive for the contractor, not just inconvenient for you.


✓  Payment milestone structure tied to verifiable completion, not dates.  Never pay on dates. Pay on verified completion milestones: when rough-in is complete and inspected, when ceiling works are complete, when finishes are applied. Each milestone requires your written sign-off before payment is released. A contractor who cannot meet milestones does not receive the next payment.


✓  Retention clause of 10% held until 30 days after practical completion.  The retention is your financial lever at the end of the project. It incentivises the contractor to return and fix defects, and it gives you funds to cover any minor completion costs if the contractor is slow on the snagging list. Never agree to release retention early, regardless of the reason given.


✓  Named project manager with a substitution clause.  If the contractor assigns a specific project manager to your job, include a clause requiring your written approval before that PM is replaced. The person presented in the pitch is often not the person who runs the project. The substitution clause means that if they swap your PM for a junior, you have a formal right to object and require reinstatement or a replacement of equal calibre.


✓  Right to audit progress against payment.  Include an explicit clause giving you the right to conduct or commission an independent site assessment before approving any progress billing. This is your evidence mechanism. Without it, a contractor can dispute your right to withhold payment even when the site assessment shows clear underpayment.


If your fit-out contractor stopped showing up to site today, would your contract give you a clear path to terminate, recover your costs, and bring in a replacement — or would you be starting from a position of uncertainty that your contractor already knew about when they signed?

TALK TO UODC ARCHITECTS

We build contracts with liquidated damages clauses, milestone-based payment structures, and clear performance obligations into every project — so our clients have recourse, not just a complaint, if something goes wrong.


Book a Free Consultation → www.uodc-architects.com/start-your-project

UODC Architects  ·  Architecture · Interior Design · Design-Build  ·  Metro Manila  ·  uodc-architects.com


 
 
 

Recent Posts

See All

Comments


bottom of page